Minnevika railway bridge

Dato:

22.03.2023

Minnevika  railway bridge - Norway’s longest railway bridge at the time of the construction. Located in Minnesund with main client Bane NOR SF. Arctic performed large parts of the concrete works as a subcontractor for PNC Norge AS. Initially our scope was concrete works on a unit rate basis for the abutment and later all crossbeams. Additionally, Arctic provided our client with ca. 20 workers on site, performing works related to concrete, Moveable Scaffold System - MSS, rigging works etc.

Minnevika bridge is 836m long concrete bridge, with over 19 spans, launched with MSS method.

Arctic started works on project in August 2020 and completion will be during 2023.