Monan ramp bridges and and Rossevann bridge
Monan ramp bridges and and Rossevann bridge – part of E39 Kristiansand Øst – Mandal Vest project realized for Nye Veier.
Arctic supported Kruse Smith AS with manpower. Our employees performed formwork, reinforcement and casting works on ramp bridges, parts of Monan bridge which is 400m long road bridge launched with the Incremental Launching Method – ILM.
Additionally, Arctic performed concrete edge beams on Rosevann bridge.
Arctic started works on project in March 2021 and finished in December 2021.